HW24: Chapter 23

Ex 23.6
Figure 23.14 shows the task durations for software product activities. Assume that a serious, unanticipated setback occurs, and instead of taking 10 days, task T5 takes up to 40 days. Draw up new bar chart showing how the project might be reorganized.